Restoration Updates - Summer 2005
As the summer heat bares down on South Louisiana,
much progress has been made on the Laura Plantation manor house. All
ceiling joists have been installed as well as the floor joists.
Ceiling boards have arrived and been installed. The walls and plates have
been pegged. Framing of the back gallery began as the porch was
re-configured for the future "u-shape" rear wings. The chimney
bases were stabilized with the new lime-silt mortar mix. Masons are
working on the interior chain walls and exterior brick pillars.
The back gallery has been installed and primed.
Two additional fire hydrants were installed on plantation grounds, tying into
the new water pipeline that was dug for sprinkler system that will be installed
in the main house. These fire hydrants are being installed at this time in
addition to the 2 fire hydrants that were currently in place along the highway.
|
|
|
|
|
|
|
|